Baltimore Scrap Storm Water System

Project Info

Kinsley installed a new underground storm water management system including cisterns and mechanical inlets for this metal recycling facility.
Approximately 800 lineal feet of drain pipe was installed to redirect contaminated storm water runoff into 13,000-gallon capacity cisterns. Next the runoff is treated through mechanical filters before being discharged into the public storm system.
Kinsley also provided continuous power supply and back-up generators for the new system.

Project:

Baltimore Scrap Storm Water Management System

Division:

Site Work

Market:

Industrial/Manufacturing

Location:

Baltimore, MD

Client:

Baltimore Scrap Corporation

Architect:

N/A

Size:

800 Lineal Feet