Kinsley Construction developed a site for a new 103,000-square-foot elementary school. The facility was built on a vacant field adjacent to the existing campus and became Maryland’s first net-zero elementary school. Our scope of work included:

Earthwork
Installing 6,000 linear feet of utility piping
Concrete curb and flatwork
Paving of parking areas and access roads