Kinsley moved a massive amount of dirt for Project Conduit, a new 1,824,000-sq-ft warehouse.
Our scope of work included:
On average, our site crews move between 2,000 and 5,000 cubic yards of dirt per day. To meet this project’s accelerated schedule, we moved more than 40,000 cubic yards of dirt per day, making this our largest earth moving project to date.
Earthwork for New Warehouse
Civil
Warehouse/Distribution
Shippensburg, PA
Matrix Development Group
Herbert, Rowland & Grub, Inc.
148 acres