Project Conduit

Project Info

Kinsley is moving a massive amount of dirt for Project Conduit, a new 1,824,000-sq-ft warehouse.

Our scope of work includes:

  • Moving 1,578,000 cubic yards of cut-to-fill dirt
  • 430,220 square yards of fine grading
  • Placing 430,220 square yards of stone base
  • Installation of four sediment basins
  • Installation of 155,200 square yards (over 32 acres) of asphalt paving
  • Installation of 54,500 linear feet (over 10 miles) of underground utilities

On average, our site crew moves between 2,000 and 5,000 cubic yards of dirt per day. To meet this project’s accelerated schedule, we are moving between 30,000 and 40,000 cubic yards of dirt per day, making this our largest earth moving project to date.

Project:

Earthwork for New Warehouse

Division:

Site

Market:

Warehouse/Distribution

Location:

Shippensburg, PA

Client:

Matrix Development Group

Architect:

Herbert, Rowland & Grub, Inc.

Size:

148 acres