Kinsley was hired to prepare a site for a future industrial park including utility work and building pads for three large warehouses.

Our scope of work consists of:

  • Demolition of three existing houses
  • Moving 900,000 cubic yards of dirt
  • Installing underground utilities and storm water management system
  • Concrete and paving
  • Widening of Route 11
  • Constructing retaining walls

Involving more than 36,000 linear feet of storm drain and fire line, the project requires two work crews to meet the aggressive schedule. We mobilized at the end of October 2021 and will complete the work in November 2022.

Project:

Site Work for an Industrial Park

Division:

Site

Market:

Warehouse/Distribution

Location:

Martinsburg, WV

Client:

R.S. Mowery & Sons

Architect:

Powers Brown Architecture

Size:

112 acres